Commercial

Toyota Tsusho Office BESS + EMS

Toyota Tsusho's office already ran 250 kW of PV but was not getting full value from it. It wanted to store surplus solar for later and manage the building's energy more actively.

Toyota Tsusho Office BESS + EMS
Outcomes

At a glance

Toyota Tsusho (Thailand)2024
20 kW
BESS power
40 kWh
BESS energy
250 kW
Existing PV
Sep 2024
COD
The challenge

What the client needed

Toyota Tsusho's office already ran 250 kW of PV but was not getting full value from it. It wanted to store surplus solar for later and manage the building's energy more actively.

Our solution

What we delivered

PEC integrated a 20 kW / 40 kWh indoor BESS with the existing 250 kW PV, and designed the EMS in-house so the client could configure how the battery and PV work together.

Why PEC

Why this project chose PEC

Here the value sat in the controls more than the battery. PEC's in-house EMS let Toyota Tsusho set the charge, discharge, and PV logic to suit the building.

Outcome

What happened in production

The BESS works with the office's solar under PEC's EMS; it went live in September 2024.